The Publish function is used to publish (post) selected schedules on the Schedule screen.

Note  

To publish all the schedules in the open schedule period, go to Schedule > Publish Schedule

To publish one or more employee schedules, complete the following steps:

  1. In the schedule grid, highlight the cell or cells with the schedules to be published.

    If a cell has more than one schedule and you want to publish only one of them, click the schedule itself to highlight it.

    A range of cells can be selected by holding Shift as you click or by clicking and dragging. These cells can span multiple days in a row and across multiple employees. Alternatively, click an employee's name to select all the days for that employee, or click a day in the date header to select all the employees for that day.

  2. Use one of following methods to publish schedules:

    Note that the Publish option is available only when there is at least one pending schedule in the selected cells.

    • Right-click to display the menu and select Publish. OR

    • From the tool bar, select the Edit menu, then the Publish option. OR

    • On the keyboard, press Ctrl-U.

    The schedules are now published and appear with bolder borders around them.